Update from the Rezydencja Bonifraterska construction site

2021-09-10

Update from the Rezydencja Bonifraterska construction site

Work at the Rezydencja Bonifraterska construction site is in full swing! This Thursday afternoon we bring you some news on the progress of the works, along with brand-new photos straight from Bonifraterska.

So what’s new? The reinforced concrete work and the window installation are 100% complete, and thermal insulation has been laid on the roof.

Work on the facade:

-East wall – completed.

-North wall – installation of anchor plates, posts, balustrades, thermal insulation, the substructure and the insulation for the ventilated facade on the ground floor, as well as embedding the mesh in adhesive – completed. Rendering and the fixing of rustication strips are under way.

-West wall – substructure brackets for the Equitone panels, installation of insulation for the cornices, posts and balustrades – completed. Installation of flashings and of insulation under the terrace decking is under way.

-South wall – installation of thermal insulation, roofing felt on the loggias, anchor plates, the Equitone substructure and insulation of the loggia ceilings – 100% complete. Insulation of the slab edges between storeys is under way.