News from the Kaskady Krakowska construction site

2022-05-18

News from the Kaskady Krakowska construction site

Wondering how construction work is progressing at Kaskady Krakowska? 🤔

The team is currently:

➡️  carrying out reinforced concrete work on garage level -2

➡️ building the vertical elements on level -1

What has already been completed?

✔️ concreting of the foundation slab

✔️ the floor slab above garage level -2

The crews are giving 100% and the weather is on our side 🌞

Another update coming soon!